Toàn cảnh nhà máy nước mặt sông Đuống FLOW CONTROL

Owner: Song Duong Surface Water JSC (an Aquaone Group member). Under the master plan the plant reaches 300,000 m³/day by 2020, built in two phases: phase 1A operating by 2018 at 150,000 m³/day, and phase 1B by 2020.

CAD supplied TECOFI mechanical and control valves for the raw-water pump station and the treatment area (settling tanks and gravity rapid filters).