Package 15, Quang Trach I Thermal Power Plant

Tender package 15 (EPC-QT1) of the Quang Trach I Thermal Power Plant project is a design, supply of goods and construction (EPC) package for two 600MW units, awarded through international open tendering, with a contract period of 48 months.

Key points
- Procuring entity: Power Project Management Board 2, a branch of Vietnam Electricity (EVN).
- Bidding documents were issued from 10 June to 7 September 2020, priced at VND 30,240,827,000,000.
- Bid security: VND 600 billion; contract period: 48 months.
- Total project investment: VND 42,022,871,000,000; as expected at the time of the tender (2020), the plant was to be completed and commissioned by 2023.
Scope of package 15 (EPC-QT1)
Package 15 (EPC-QT1), Design, Supply of Goods and Construction (EPC), is procured through international open tendering. Participating contractors must submit a bid security of VND 600 billion.
The package covers: detailed engineering design, construction drawing design, supply, construction, installation, operation, commissioning, performance testing and full handover of two 600MW (net capacity) units, and warranty; the transmission lines that connect to the 500kV distribution substation; and operator training and technology transfer.
Project information
Power Project Management Board 2 – a branch of Vietnam Electricity (the procuring entity) announced that it issued the bidding documents for package 15 from 10 June to 7 September 2020, at a price of VND 30,240,827,000,000.
The Quang Trach I Thermal Power Plant project has a total investment of VND 42,022,871,000,000, with Vietnam Electricity as the investor. At the time of the tender (2020), the project was expected to be completed and the plant put into operation by 2023.
Source: baodauthau.vn (Vietnam Bidding Newspaper)
Frequently asked questions
What does tender package 15 of the Quang Trach I Thermal Power Plant include?
Package EPC-QT1 covers detailed engineering design, construction drawing design, supply, construction, installation, operation, commissioning, performance testing and full handover of two 600MW (net capacity) units, warranty, transmission lines connecting to the 500kV distribution substation, operator training and technology transfer.
What are the total investment and the contract period?
The project has a total investment of VND 42,022,871,000,000, with Vietnam Electricity as the investor; the contract period of package 15 is 48 months. As of 2020, completion was expected by 2023.